Brief description:
Detailed engineering, equipment and material supply, building, mounting and start up of high pressure gas pipe (Gasoducto Norte) Expansion 5,2MM m3/day, operated by TGN S.A.
Total expansion 4 stages: 101,5 km gas pipe 30″ and 24″.
Main characteristics – Section 78
Contractual Name N11a from Recreo, Córdoba, to Dean Funes, Córdoba.
27 km high pressure gas pipe.
30″ diameter
Main characteristics – Section 42ab
Contractual Name N05ab from Miraflores, Salta, to Lumbreras, Salta.
14km high pressure gas pipe.
24″ diameter
Main characteristics – Section 46
Contractual Name N09a from Tucuman, Stgo Del Estero to Lavalle, Stgo. Del Estero.
11,2km high pressure gas pipe
24″ diameter
Main characteristics – Section 83a
Contractual Name N13d from Ferreyra, Salta to Tio Pujio, Salta.
33,5 km high pressure gas pipe
30″ diameter
Main characteristics – Section 86
Contractual Name N33 from San Jerónimo, Salta to Pacheco, Salta
15,8 high pressure gas pipe
30″ diameter